Pricing & Terms

Asphalt Transparent

(Rates as of 4/17/2024)

1
Material Costs

$4 Per Yard Pumped

2
Labor Costs

A) Hourly Rates:

  • Travel Time: $135 per hour (minimum one hour)

  • On Site: $185 per hour (minimum three hours)

B) Overtime:

Additional $40 per hour. Overtime hours are applied if job runs more than eight hours, or is outside normal business hours (Monday through Friday 7am to 5pm, Saturday 7am to 11am).

C) Prevailing Wage:

Additional $45 per hours. Prevailing wage rate based on heavy highway work. Hourly rates start when the pump arrives on site an ends when the pump leaves.

3
Fuel Costs

Diesel fuel price based on EIQ.gov Midwest region average.

  • If fuel price is between $3.25 and $3.75 per gallon, an additional pump rate of $5 per hour will apply.

  • If fuel price is between $3.76 and $4.50 per gallon, an additional pump rate of $10 per hour will apply.

  • If fuel price is between $4.51 and $5.25 per gallon, an additional pump rate of $15 per hour will apply.

4
Addition System Costs (Line Pumping Only)

The first 50 feet of line pump system is free of charge.

If additional system beyond 50 feet is needed, an hourly rate will apply for delivery and material. This does not include the additional labor charges. Any additional labor for setup and teardown will be billed at $85 per hour.

5
Customer Responsibilities

A) Pumpable Mix & Disposal Area

Customer is responsible for supplying a pumpable mix, and providing a washout and concrete disposal area.

B) Stable & Clear Worksite

Site must be stable enough to support pump outriggers, and be clear of overhead obstructions.

C) Damage to Equipment

Customer is responsible for the cost of any damage to equipment due to negligence, including both parts and labor costs.

6
Cancelation Policies & Fees

Cancellation calls must be made during normal business hours, Monday through Friday 7am to 5pm and Saturday 7am to 11am.

  • Jobs not canceled 12 hours prior to pour time are subject to a $200 cancellation fee (excluding weather conditions).

  • Cancellations done while the pump is en-route to a job are subject to a $300 cancellation fee.

  • If the site is not safe to operate on, has no safe access for a pump truck, or not prepared for a pump truck, customer is subject to a $300 cancelation fee.

on-point-logo.png

On Point Concrete Pumping offers professional boom and line pumps for residential and commercial floors, walls, and footers.

Resources

Connect

Address: 8024 OH-73 #200, Wilmington, OH 45177

Office Hours: Mon–Fri 7:30am to 4pm

Phone: (937) 566-9811

Email: Contact Us

Copyright © 2025 On Point Concrete Pumping. All Rights Reserved.

bottom of page